Scheduled Projects & Plans for 2008-09 |
| Print |
|
|
Information regarding scheduled fluvial stream geomorphic assessments and river corridor planning projects for 2008-2009 are provided as a guide.
Currently, $223,642.00 in grants are funding six different Restoration and Education Projects and seven different geomorphic assessments.
Geomorphic Assessments
Whetstone Brook Watershed | Phase 1 & 2 and River Corridor Planning
Completion Date – June 2008
Crosby Brook Watershed | Phase 1 & 2 Stream Geomorphic Assessments
Completion Date – June 2008
Ball Mountain Brook | River Corridor Planning/Implementation
Completion Date – December 2008
Whetstone Brook Watershed | River Corridor Planning/Implementation
Completion Date - May 2009
Rock River Watershed | River Corridor Planning
Completion Date – June 2009
Crosby Brook Watershed | River Corridor Planning
Completion Date - June 2009
Saxtons River Watershed | Phase 1 and Phase 2 Stream Geomorphic Assessments
Completion Date – September 30, 2010
Restoration and Educational Projects
Whetstone Floodplain Outreach Project
District to develop and distribute educational materials specific to
the Whetstone Brook Floodplain (Booklet, slideshow and interactive
tabletop Model)
Completion Date – June 2008
Trees for Stream on the Williams, Saxtons or West River
Two stream bank buffer plantings
Completion Date – August 2008
Crosby Brook Watershed Head-cut Restoration Project
Assist in the stabilization of the head-cut on Crosby Brook
Completion Date – September 2008
Skidder Bridge Rental Program
District to obtain all building materials for one skidder bridge and
all bridge hardware /metal fabrication costs of second bridge and
construct one bridge.
Completion Date – March 2009
Whetstone Brook Corridor Protection Project
District will hire a professional property appraiser to determine the
appropriate price of two parcels along the Whetstone Brook near the
intersection of Route 9 and Sunset Lake Road that are currently for
sale.
Completion Date – March 2009
Trees for Stream on the Williams, Saxtons or West River
Two stream bank buffer plantings
Completion Date – November 2009
Total Grants- $223,642.00
|
|
Last Updated ( Tuesday, 15 April 2008 )
|