Home arrow Basin 11 arrow Scheduled Projects & Plans for 2008-09
Scheduled Projects & Plans for 2008-09 | Print |

Information regarding scheduled fluvial stream geomorphic assessments and river corridor planning projects for 2008-2009 are provided as a guide.

Currently, $223,642.00 in grants are funding six different Restoration and Education Projects and seven different geomorphic assessments.

Geomorphic Assessments

Whetstone Brook Watershed | Phase 1 & 2 and River Corridor Planning
Completion Date – June 2008

Crosby Brook Watershed | Phase 1 & 2 Stream Geomorphic Assessments
Completion Date – June 2008

Ball Mountain Brook | River Corridor Planning/Implementation
Completion Date – December 2008

Whetstone Brook Watershed | River Corridor Planning/Implementation
Completion Date - May 2009

Rock River Watershed | River Corridor Planning
Completion Date – June 2009

Crosby Brook Watershed | River Corridor Planning
Completion Date - June 2009

Saxtons River Watershed | Phase 1 and Phase 2 Stream Geomorphic Assessments
Completion Date – September 30, 2010

Restoration and Educational Projects

Whetstone Floodplain Outreach Project
District to develop and distribute educational materials specific to the Whetstone Brook Floodplain (Booklet, slideshow and interactive tabletop Model)
Completion Date – June 2008

Trees for Stream on the Williams, Saxtons or West River
Two stream bank buffer plantings
Completion Date – August 2008

Crosby Brook Watershed Head-cut Restoration Project
Assist in the stabilization of the head-cut on Crosby Brook
Completion Date – September 2008

Skidder Bridge Rental Program
District to obtain all building materials for one skidder bridge and all bridge hardware /metal fabrication costs of second bridge and construct one bridge.
Completion Date – March 2009

Whetstone Brook Corridor Protection Project
District will hire a professional property appraiser to determine the appropriate price of two parcels along the Whetstone Brook near the intersection of Route 9 and Sunset Lake Road that are currently for sale.
Completion Date – March 2009

Trees for Stream on the Williams, Saxtons or West River
Two stream bank buffer plantings
Completion Date – November 2009

Total Grants- $223,642.00

Last Updated ( Tuesday, 15 April 2008 )
 